What does the current auction actually say?
PJM procured capacity is below its own reliability requirement. Installed ICAP, accredited UCAP, and queue nameplate are not interchangeable.
Read this decision layer →The honest answer is conditional. Capacity must be accredited, deliverable, stress-performing, and online when the load arrives—with a tested flexible-load fallback.
The current evidence does not support a clean yes-or-no answer to “Can PJM absorb the surge?” It supports a contract and sequencing answer: match energization to accredited supply, demonstrate deliverability, and require tested data-center flexibility until both are in service.
PJM procured capacity is below its own reliability requirement. Installed ICAP, accredited UCAP, and queue nameplate are not interchangeable.
Read this decision layer →An Elliott-window counterfactual and a dated Dominion import-capability screen expose two risks that a system total hides.
Read this decision layer →It can show a planning-level capital requirement and market signal. It cannot turn those into a retail-rate forecast.
Read this decision layer →Only capability that is grid-connected, accredited, deliverable, and available when needed earns a reliability credit in this screen.
Read this decision layer →Flexibility is applied only to incremental data-center load and only in hours that would otherwise cross the ceiling.
Read this decision layer →The auction shortfall removes the premise that current accredited capacity offers unclaimed headroom.
Nine complete demand years show when a transparent 170 GW scenario ceiling is crossed. This produces shortage-screen hours, not LOLE.
Exact combinations of bridge capacity, new firm capability, and DC-only flexibility show which conditions move the answer.
Elliott adds performance risk; Dominion adds locational deliverability. A fabricated cascade model adds neither and was retired.
A project approval still requires PJM accreditation, transmission, and interconnection studies. This public screen does not impersonate them.
The former nine-hour proxy is gone. Shortage hours and events are labeled as screen outputs.
The hand-built logistic cascade and population-impact claims are removed.
Demand response can now reduce only the incremental DC load, never an arbitrary percentage of total PJM demand.
The page, interactive JSON, tests, source hash, script hash, assumptions, and correction log now travel together.