Skip to content
Study 2: Beyond 19 GW → Question 2

How Much Does Concentration Cost?

Dominion's HVDC project adds 3 GW of transfer capacity for $4.8B. We swept the transfer limit from 3 GW to 20 GW at each DC load level, then converted the gap to dollars using the HVDC as cost reference ($1.6B/GW).

Question 2 — Analysis on Q1

Transfer Sweep: DOM Hours vs. Capacity

DOM hours unserved by transfer capacity — 5 GW DC, 70/30
DC LoadCurrent (6.6 GW)+HVDC (9.6 GW)Transfer NeededCapex$/MWh
3 GW142 hrs0 hrs9.6 GW$4.8B$0.29
5 GW374 hrs16 hrs11.1 GW$7.2B$0.52
7 GW888 hrs119 hrs12.1 GW$8.8B$0.66
10 GW2,468 hrs541 hrs14.6 GW$12.8B$1.03
Finding 1

PJM's planned $4.8B HVDC upgrade (3 GW additional transfer capacity) resolves the bottleneck only up to 3 GW of data center load. Dominion already has 4 GW committed by 2028—the HVDC is undersized before it's built.

Sanity check: the model matches the real HVDC project.

Our model says 3 GW DC needs +3 GW transfer costing $4.8B. Dominion is building exactly that. This confirms consistency with Dominion's own capacity adequacy assessment—the model uses the same public inputs (CETL, load forecasts). It is not an independent prediction.

The HVDC is already undersized for the committed pipeline.

Dominion has 4 GW committed by 2028. The HVDC comes online June 2032 and handles ~3 GW. At 7 GW DC, even with the HVDC, Dominion still shows 119 hours unserved. Full reliability requires ~12 GW total transfer—almost double.

Finding 2

At 7 GW DC load, even with the HVDC upgrade, Dominion still faces 119 hours unserved. Closing the gap entirely requires ~12 GW total transfer capacity—double the planned HVDC investment.

Finding 3

The per-MWh cost of transmission to enable distributed siting ($0.25–$0.66/MWh) is an order of magnitude cheaper than the reliability cost of concentrated siting. Distribution is not just safer—it's cheaper.