Skip to content
Studies · Case Study

Can the Texas Grid Handle AI?

ERCOT is America's only major isolated grid — 27 million people, no backup from neighboring states. In February 2021, Winter Storm Uri brought it within 4 minutes and 37 seconds of total collapse, leaving 246 dead and $130 billion in damage.

Now AI data centers have filed for 226 GW of new interconnections — 73% of the queue, nearly triple ERCOT's current peak demand. Can the grid handle it?

The answer depends on whether you model the grid as a whole — or model where the load actually lands.

85 GW
Peak Demand (2024)
226 GW
In Queue (73% DCs)
464 TWh
Annual Generation
4:37
From Collapse (2021)
Before We Start

Five Models. Two Dimensions of Fidelity.

This study uses five distinct simulation models. But model complexity is only one dimension of fidelity. The other — and for this study, the more important one — is how honestly you treat uncertainty in the inputs.

The Models

Q1–Q4

Hourly Dispatch

Merit-order simulation of all 8,760 hours. Nuclear first, then renewables, batteries, gas, coal. Shortfall = blackout. The workhorse behind the first four questions.

Q5

Spatial Dispatch

Splits ERCOT into 2 or 6 zones with capacity-limited transmission corridors. Same dispatch algorithm, now topology-aware. Reveals bottlenecks the single-node model can't see.

Q6

SCUC Optimizer

Mixed-integer programming. Gas plants cost $80K to start, can't run below 40%, must stay on 8+ hours. Tests whether real machine constraints change the answer.

Q7

Cascade Solver

Iterative coupled solve. Gas shock → dispatch → load shedding → compressor failure → more gas offline → repeat until convergence or collapse.

Q8

Backward DP

Dynamic programming for optimal battery dispatch. Perfect foresight over the full year, plus receding-horizon variants with limited forecast windows.

Deterministic vs. Stochastic

Several questions were analyzed both ways. Deterministic analysis uses one weather year, or sweeps across ten years (2015–2024, demand-normalized to 2024 peak), with all plants working perfectly. Stochastic Monte Carlo runs 200 draws per scenario with random weather year selection, 7–10% forced outage rates, and ±3% demand noise — this is how real resource adequacy studies work.

The biggest fidelity gap in this study isn't between models. It's between deterministic and stochastic analysis of the same model. The dispatch algorithm didn't change. What changed is whether we pretended every plant works every hour. That single assumption — all plants available — is what makes the grid look reliable when it isn't.

What Changes the Answer — and What Doesn't

60 GW gas + 300 GWh storage at 70% renewables + 15 GW data center load:

6
Deterministic
(best year)
49
Deterministic
(worst year)
6
SCUC Model
(best year)
476
Stochastic MC
(P90)

The escalation converges. Weather variability matters — it reveals failures a single good year hides (6→49). A more complex model (SCUC) doesn't change the answer — the optimizer confirmed the simpler dispatch was right (49→6). But adding forced outages to the same dispatch model changes everything (6→476). The model was fine. The inputs were a lie.

The Investigations

Eight Questions. Eight Deep Dives.

Each question was answered at the fidelity it required. Click any card to see the full analysis, charts, and methodology.

Core Questions
Higher Fidelity

Scope: Five models totaling ~4,500 lines of Python, including MIP-based SCUC (PuLP/CBC), iterative cascade solver, 6-zone spatial dispatch, stochastic Monte Carlo (200 draws with forced outages and demand noise), and backward DP dispatch optimization. Ten years of ERCOT weather data (2015–2024), demand-normalized to 2024 peak. Eighteen years parsed (2007–2024); years before 2015 excluded after testing showed demand dilution without additional weather diversity. Limitations documented honestly: simplified demand response, no new nuclear/SMR, no sub-hourly dynamics, greedy (not LP) zonal transfers. Each question got the model it needed — nothing more.

The Fidelity Lesson

Finding the Right Model for the Decision

Each question above was answered at the fidelity it required. But scattered across eight questions, it's easy to miss the pattern: which dimensions of reality actually change the answer? Here it is in one place — the same investment evaluated at increasing fidelity, showing where the answer converges and where it breaks.

60 GW gas + 300 GWh storage — $66B (incremental CAPEX, undiscounted)

Model FidelityBlackout HoursWhat a Planner Concludes
Hourly dispatch, best weather year 6 “Meets the reliability standard.”
+ Monte Carlo (10 weather years) 49 “Fails in 7 of 10 years. Not reliable.”
+ SCUC optimizer (24h MIP) 6 “Still reliable. UC constraints don't bind with 300 GWh.”
+ Stochastic MC (200 draws, forced outages) P90: 476 “Catastrophically unreliable when you model real plant availability.”
+ Gas-electric cascade (Q7) amplifies shock 2× “A 25% gas outage becomes 52% via feedback.”

Every model up to SCUC said 6 hours — reliable. Then we added forced outages and demand uncertainty: P90 jumps to 476 hours. The gap isn't between dispatch models anymore — it's between deterministic planning and stochastic reality. Real power plants break. Real demand deviates from forecast. A planning process that ignores both is planning for the best case, not the likely one.

70 GW gas + 50 GWh storage — $24B (incremental CAPEX, undiscounted)

Model FidelityBlackout HoursVerdict
Hourly dispatch, best weather year 2 Reliable
+ Monte Carlo (worst weather year) 8 Reliable
+ SCUC optimizer (24h MIP) 0 Reliable (optimizer uses batteries better than greedy dispatch)
+ Stochastic MC (200 draws, forced outages) P90: 270 Not reliable. Need 85 GW gas to pass P90.
6-zone spatial model (Q5) Robust if load is distributed across zones
+ Gas-electric cascade (Q7) amplifies shock 1.7× Manageable at 1.5% coupling; collapses at 3%+
The Fidelity Lesson
Deterministic models said 70 GW gas + 50 GWh storage was the cheapest reliable option. Stochastic Monte Carlo — the same model with real-world uncertainty — says it fails at P90. You need 85 GW of gas and 50 GWh of storage to survive 9 out of 10 draws. The answer didn't change because we used a fancier algorithm. It changed because we stopped pretending every plant works every hour.

Methodology note: This analysis uses 10 years of weather data (2015–2024) with demand normalized to 2024 peak levels (85.5 GW). We parsed 18 years of ERCOT generation data (2007–2024), but years before 2015 add weather diversity already captured by the 10-year window—the worst February wind drought in the 18-year record (2018) is nearly identical to one in the 10-year sample (2023). Demand normalization ensures every Monte Carlo draw faces current demand levels, not the 15–30% lower demand of earlier years. Without normalization, draws from low-demand years make the grid look artificially reliable.

Understanding P90: Why Reliability Matters

P90 means the 90th percentile of stress hours. Out of 10 weather years, 9 are "easier" than this. Only 1 year is worse. This is the reliability standard that grid operators must meet.

P10
50h
P50
200h
P90
476h
Worst
~600h

What it means: If you design the grid for P50 (200 hours of stress), you'll fail 50% of the time. If you design for P90 (476 hours), you're safe 90% of the time — but you need way more gas capacity and battery storage.

The decision: ERCOT must choose between (a) frequent blackouts, (b) massive overbuilding, or (c) acceptance of 1-in-10 stress years. That's why P90 is the industry standard — it's the reliability level most societies accept.

Sensitivity Analysis

What Drives the Answer?

Across eight investigations, three inputs dominate the capacity question. Two widely-discussed factors barely move the needle.

Weather & Outages Run the Show

Pick a different weather year and the breaking point swings from 6 GW down to 2 GW. Layer in realistic forced outages (7–10%) and it drops to zero. Nothing else in the model moves the answer that much.

Q1–Q2: Breaking Point & Investment

Location Changes Everything

67 blackout hours or 528? Same 10 GW of data centers, same year. The only difference: one model treats ERCOT as a single node, the other splits it into two zones with transmission limits. That 8x gap is entirely about where you build, not how much.

Q5: Location

Dispatch and Gas Prices? Barely Register

A 6-hour battery forecast captures 97% of perfect-foresight value. Gas price swings shuffle the dispatch order but don't change whether the grid holds. These are operational dials, not structural ones.

Q8: Dispatch Intelligence

See the full sensitivity table →

Can You Trust These Numbers?

Model Validation

Before projecting future scenarios, we ran the dispatch model against 2024 actuals. Same model, same algorithm — but compared to what EIA recorded actually happened on the grid.

MetricModelEIA ActualErrorExplanation
Wind generation 111.8 TWh 111.8 TWh +0.0% Same underlying profiles
Solar generation 47.8 TWh 47.8 TWh +0.0% Same underlying profiles
Nuclear generation 39.0 TWh 38.9 TWh +0.2% Constant 87% CF assumption
Gas generation 281.8 TWh 204.3 TWh +37.9% Model dispatches gas before coal (see below)
Coal generation 0.2 TWh 58.9 TWh −99.7% Model barely dispatches coal
Gas + Coal combined 282.0 TWh 263.2 TWh +7.2% Total thermal need is close
Peak demand 85.5 GW 85.5 GW +0.0% Same input profile

The honest reading: Our merit-order model dispatches gas before coal, so it over-predicts gas by 38% and under-predicts coal by 100%. But total thermal generation (gas + coal combined) is within 7.2% of reality. For the future scenarios in this study — which assume coal retires to zero — this error disappears: all thermal generation is gas, and the model's total thermal estimate is what matters. The validation confirms the model correctly predicts how much dispatchable generation the grid needs, even if it misallocates between fuel types in the current fleet.

Validation uses 2024 installed capacity: wind 34 GW, solar 30 GW, gas 56 GW, nuclear 5.1 GW, coal 11 GW, battery 13 GW / 52 GWh. EIA-930 hourly actuals. Battery discharge is over-predicted (model assumes full 13 GW fleet; actual 2024 operational fleet was ~3 GW still ramping).

Limitations

What This Model Doesn't Capture

Every simplification was a deliberate choice. These are the ones that matter most.

Simplified Demand Response

DR is modeled as a fixed percentage of peak load that can be shed. Real demand response involves complex contract structures, participation rates, and fatigue effects over multi-day events. The model likely overstates DR availability during sustained stress.

No New Nuclear or SMR

The generation fleet is based on current installed capacity plus announced additions. Small modular reactors and new conventional nuclear are excluded. If SMR deployment accelerates, the capacity gap narrows — but not on the timeline of the data center queue.

No Sub-Hourly Dynamics

Dispatch runs at hourly resolution. Frequency regulation, ramping constraints, and intra-hour renewable variability are not captured. This matters most for battery valuation — batteries provide sub-hourly services that the model cannot see.

Greedy Zonal Transfers

Inter-zone power flows use a greedy algorithm, not linear programming. The model routes power to the nearest deficit zone without optimizing system-wide transfer efficiency. Real ERCOT dispatch is more efficient than what the model computes.

CAPEX Only, No Lifecycle Costs

Investment estimates use NREL ATB 2024 overnight capital costs. Fuel costs, O&M, financing, and capacity factor degradation are excluded. These are order-of-magnitude comparisons between options, not project-level investment cases.

No Market Feedback

Generators and load-serving entities are price-takers. In reality, scarcity pricing triggers investment responses and demand shifts that the model does not capture. This is a structural stress test, not an equilibrium forecast.

Reality Check — March 2026

What's Actually Happening

The analysis above answers “what if.” This section answers “what is.” Real data center investments have been announced. Real generation is under construction. Real legislation has been signed. Here's how reality maps onto our model.

What's Coming: Data Center Demand

ERCOT's large-load interconnection queue hit 226 GW in 2025 — up 259% in a single year, with 73% of it data centers. But historically only 13% of queued generation projects reach commercial operation (Lawrence Berkeley National Lab). ERCOT itself applies a 49.8% haircut to requested amounts. Here's what's actually under way.

ProjectLocationCapacityTimeline
OpenAI / Oracle (Stargate)Abilene1.2 GWFirst buildings operational Sep 2025
Google (3 campuses)West TX / PanhandleMulti-GW$40B investment, 2025–2028
MetaEl PasoGW-scaleExpected 2028
Amazon / AWSRound Rock, DeSoto, AmarilloVariousIn planning / zoning

Analyst estimates converge on ~10 GW of data center load by 2028, with ~6 GW/year additions possible thereafter, constrained by gas turbine manufacturing (Modo Energy). ERCOT projects 55 GW of DC load by 2030; independent analysts call this unrealistic, estimating 20–30 GW based on supply-chain and construction limits (Ascend Analytics).

In our model, 10 GW of data center load at the current generation mix produces 71 blackout hours per year — 8× the reliability standard. At 20 GW, it's 700+ hours. These aren't hypotheticals anymore.

It's Not Just Data Centers

Data centers dominate the growth narrative — roughly 60–70% of ERCOT's incremental demand through 2030. But they're not the whole story.

Demand DriverAdditional Load by 2030Context
Data centers 40–55 GW (queue-adjusted) 73% of the interconnection queue. The dominant driver.
Oil & gas electrification ~8.5 GW Permian Basin drilling, pumps, compressors shifting from diesel to grid power.
Cryptocurrency mining 4.3–5.3 GW 9% of queue. ~3 GW is price-responsive (curtails during scarcity).
Population growth ~3–4 GW (organic) 391,000 new Texans per year. 1.2% growth, #1 state in absolute additions.
Electric vehicles ~2 GW peak 456K EVs registered (2025), growing ~1,500/week. Small relative to grid scale.

Before the data center boom, ERCOT demand grew at roughly 3% per year — driven by population, Permian Basin electrification, and increasing cooling load. That baseline alone would stress the grid over a decade. Data centers accelerated the timeline from “gradual challenge” to “imminent crisis.”

What's Being Built: New Generation

ResourceCapacityTimelineStatus
Texas Energy Fund (new gas)10 GW (17 projects)2028–2029$5.4B in loans approved; 3.3 GW finalized
Gas (under construction now)1 GWSummer 2026Under construction
Battery storage14 → 19 → 40–55 GWNow → mid-2026 → 202914 GW operational, on track
Solar (under construction)23 GWSummer 2026Under construction

The pattern: Texas is building renewables and batteries at scale, but almost no new dispatchable gas arrives before 2028. The TEF pipeline addresses this, but 10 GW of new gas brings the total to ~66 GW — and our stochastic analysis shows you need 85 GW (P90) to 90 GW (P99) to survive forced outages and weather variability at 15 GW of data center load.

ERCOT Projected Reserve Margin (December 2025 CDR)

Reserve margins go negative by summer 2028. ERCOT's own December 2025 Capacity, Demand and Reserves report projects the grid drops below its 13.75% target in 2027 and enters shortfall territory by 2028. This is not a model projection — it's ERCOT's published assessment based on what's under construction versus what's been requested.

The Gap

Mapping real-world supply plans onto our model results:

Timeframe Likely DC Load Gas + Storage Available Our Model Says
2026–2027 6–10 GW 56 GW gas, ~76 GWh battery At the edge. SB 6 curtailment is the safety valve.
2028–2029 10–20 GW ~66 GW gas (with TEF), ~200 GWh battery Falls short. Stochastic MC says you need 85 GW (P90) at 15 GW DC.
2030+ 20–30 GW ~66 GW gas, ~220 GWh battery Deeply insufficient. 700+ blackout hours at 20 GW without major new gas.
The Gap
The Texas Energy Fund closes most of the gas gap through 2028 — if all 17 projects deliver on time. Beyond that, there is no funded plan for the additional 4–14 GW of dispatchable capacity that 20+ GW of data centers would require. The binding constraint isn't policy or money — it's gas turbine manufacturing capacity, limited to roughly 6 GW per year for all of ERCOT.

SB 6: The Legislature's Answer

Senate Bill 6, signed June 2025, directly addresses several risks our analysis identified.

SB 6 ProvisionWhat Our Model Found
50% on-site backup for loads ≥ 75 MW Q4 found 30% flexibility cuts blackouts by a third. 50% backup exceeds this.
ERCOT curtailment authority during emergencies DR reassessment: 5% demand response doubles grid DC capacity from 4 to 8 GW.
Remote disconnect for new large loads Enables rapid load shedding our Q3 stress test showed is critical during Uri-type events.
Interconnection cost-sharing Q5: Location matters. Cost-sharing discourages concentration in constrained corridors.

SB 6 is well-designed for the near term. Its provisions map directly onto the mechanisms our analysis identified as most effective. The question is whether it's sufficient beyond 15–20 GW, where the gas capacity gap becomes dominant and on-site backup generators can't substitute for grid-scale dispatchable power.

Recommendations

What We'd Recommend

Eight questions, four model fidelities, ten years of weather data, hundreds of scenario combinations — and now grounded in what's actually being built, bought, and legislated.

Bottom Line
Texas can handle the first wave of data centers (6–10 GW) with current infrastructure plus SB 6's curtailment authority. The second wave (10–20 GW) depends entirely on the Texas Energy Fund delivering 10 GW of gas on schedule — and our stochastic model says even that isn't enough. With forced outages, you need 85 GW (P90) to 90 GW (P99) of gas, not 70. That's 19–24 GW beyond what's funded. A third wave beyond 20 GW has no credible supply plan today.

How Sensitive Are These Numbers?

Every model depends on assumptions. We tested how the stochastic reliability of our recommended configuration (85 GW gas + 50 GWh storage, 70% RE + 15 GW DC) changes when we vary three key assumptions. The baseline passes LOLE at P90 with 6 blackout hours. Here is what moves it.

AssumptionValueP90 HoursVerdict
Demand growth0% / yr 6 PASS — baseline
Demand growth2% / yr 77 FAIL — +8% demand by 2028 overwhelms supply
Demand growth4% / yr 275 FAIL — catastrophic; 275 blackout hours at P90
Battery RTE80% 9 BORDERLINE — just at the LOLE threshold
Battery RTE85% 6 PASS — baseline
Battery RTE90% 5 PASS — modest improvement
Fleet EFOR5% 2 PASS — well-maintained fleet, plenty of margin
Fleet EFOR8% 6 PASS — baseline
Fleet EFOR12% 32 FAIL — aging or stressed fleet breaks reliability

What matters most: Demand growth dominates. Even 2% annual growth (+8% by 2028) pushes P90 blackout hours from 6 to 77 — more than 12x the LOLE standard. Battery efficiency barely moves the needle (P90 range: 5–9). Fleet reliability matters at the margin: if forced outage rates climb from 8% to 12% (aging fleet, stressed conditions), the configuration fails. The implication: ERCOT's biggest risk isn't the supply plan — it's whether demand growth outpaces it.

What Texas Is Getting Right

ActionWhy It Works (Per Our Analysis)
Texas Energy Fund ($9B for gas) Gas is the dominant reliability lever (Q2). 10 GW of new gas is the single most impactful investment possible.
SB 6 curtailment + backup mandates Demand response is the cheapest tool (Q4). Legislating it removes voluntary participation risk.
Battery buildout (14 → 55 GW by 2029) Short-duration storage handles daily peaks. Texas is building this faster than anywhere else.
SB 6 interconnection cost-sharing Discourages corridor concentration (Q5). Market signal for distributed siting.

What's Missing

GapWhy It MattersWhat To Do
No gas plan beyond TEF TEF delivers ~66 GW total. Stochastic MC needs 85 GW (P90) for 15 GW DC — that's 19 GW short. The cascade model (Q7) shows 66 GW is especially fragile to gas-electric feedback. TEF Round 2 targeting 19–24 GW additional gas by 2030.
Gas turbine supply bottleneck Only ~6 GW/year available for ERCOT. Manufacturing, not money, is the constraint. Long-lead procurement now. Prioritize combined-cycle for reliability (Q6).
No long-duration storage strategy 4h batteries can't address multi-day deficits. Uri was a 72-hour event. Incentivize 8–12h storage. Duration matters more than capacity.
Gas weatherization + cascade resilience Q3: 25% gas outage is manageable, 50% is catastrophic. Q7: the cascade amplifies a 25% shock to 52% at 2% coupling. Weatherization AND compressor backup power are the dividing lines. Mandatory standards with compliance verification. Backup power for critical compressor stations. Cheapest insurance available.
No plan for 20+ GW DC load At 20 GW with current plans, our model shows 700+ blackout hours in good weather. Conditional interconnection: DCs beyond 15 GW total require demonstrated generation adequacy.

Where the Next Dollar Should Go

Based on our analysis and the current supply pipeline, in priority order:

PriorityInvestmentEst. CostReliability Impact
1 Gas weatherization (existing fleet) $2–4B Keeps outage rate below 25% in winter storms. Prevents 90% of Uri-scale damage (Q3).
2 19–24 GW additional gas (beyond TEF) $23–29B Closes gap from 66 to 85–90 GW. Stochastic MC says 85 GW for P90 reliability, 90 GW for P99 at 15 GW DC.
3 Long-duration storage (8–12h, 50+ GWh) $12–15B Addresses multi-day deficits that 4h batteries cannot. Complements gas for winter resilience.
4 West TX transmission expansion $3–6B Raises the 20 GW transfer corridor limit. Enables West TX DC siting beyond 10 GW (Q5).

Cost estimates are incremental CAPEX only (NREL ATB 2024 assumptions, undiscounted). They exclude fuel costs, O&M, financing, and capacity factor degradation. These are order-of-magnitude figures for relative comparison between options — not project-level investment estimates. A proper cost-benefit analysis would require discounted cash flow modeling with fuel price scenarios.

The Right Fidelity for This Decision
An annual screening model says Texas has plenty of capacity. Hourly dispatch says it's tight. Monte Carlo across weather years says it fails. Stochastic Monte Carlo with forced outages says the “cheapest reliable” option isn't reliable at all — P90 of 270 blackout hours. The cascade model reveals a risk invisible to all dispatch models: the gas-electric feedback loop that turns a bad storm into total grid collapse. Each model tells you something the simpler one can't — and the stakes are tens of billions of dollars and the reliability of a grid serving 27 million people.

Analysis current as of March 2026. Data center announcements, generation construction, and policy are evolving rapidly. ERCOT queue data, CDR reports, and EIA generation data are updated quarterly. This analysis will be updated as material changes occur.

Sources

Sources

Grid Operations Data
EIA-930 Hourly Grid Monitor — Generation by fuel type + demand, 2019–2024 (52,608 hours). ERCOT Capacity, Demand and Reserves Report (Dec 2025) — Reserve margin projections, installed capacity. NREL Annual Technology Baseline 2024 — Battery parameters and capital costs. FERC/NERC Joint Inquiry into February 2021 — Uri failure analysis, gas supply chain data.

Demand Forecasts
ERCOT 2025 Long-Term Load Forecast (Apr 2025) — Peak demand projections, EV forecast (Table 1), large load queue methodology. ERCOT 2026 Long-Term System Assessment — 207 GW new resource need. Ascend Analytics — Independent critique of ERCOT load projections (119 GW realistic by 2030).

Data Center Investments
Utility Dive — ERCOT large load queue 226 GW, 73% data centers. Modo Energy — DC buildout projections, gas turbine supply constraint (~6 GW/yr). Lawrence Berkeley National Lab — Interconnection queue completion rates (13% historical). JLL Year-End 2025 — 6.5 GW under construction in Texas.

Non-DC Demand Growth
EIA — Rapid electricity demand growth in Texas. Yale Clean Energy Forum — O&G electrification, 3.4→11.9 GW by 2032. EIA — Cryptocurrency mining electricity consumption. TxETRA — Texas EV registration data. Texas Tribune / Census — Texas population growth (31.7M, +391K/yr).

Policy & Legislation
McGuireWoods — SB 6 overview (75 MW threshold, 50% backup, curtailment authority). Power Magazine — Texas Energy Fund, $5.4B for 10 GW. Texas Tribune — $7.2B gas plant loan program details.

Battery & Generation Pipeline
Modo Energy — ERCOT battery buildout (14 GW operational, 40–55 GW projected by 2029). EIA — ERCOT meeting demand with solar, wind, and batteries. Texas Comptroller — The Future of Texas Power.